Nagpur:
The alarming backlog has raised serious questions over the functioning of the newly introduced work module system, which was supposed to streamline project approvals, monitoring and execution but has instead emerged as another stumbling block in the movement of development files.
The scale of the pendency has triggered resentment among corporators across party lines, who are increasingly frustrated with the slow pace of development work despite the availability of administrative approvals. The issue has now escalated into a confrontation between elected representatives and the civic administration.
In a fresh attempt to bring financial planning back on track, the NMC Accounts and Finance Department issued a circular on Monday directing all departmental heads to prepare revised budget estimates for 2026-27 and submit proposals for the 2027-28 budget. The exercise assumes significance as hundreds of approved projects have yet to cross the basic procedural hurdle of tendering, leaving the administration with a shrinking window to issue work orders before March 31.
According to officials, nearly 900 development-work files have secured administrative approval but are still awaiting completion of tendering formalities. Without timely issuance of work orders, these projects cannot move towards execution within the current financial year. The consequences could be significant, as the corresponding financial commitments and liabilities would have to be carried forward, further burdening the next year’s budget.
Corporators up in arms over work module
The growing frustration among corporators has exposed the disconnect between the civic administration’s claims of streamlining development activities and the ground reality of stalled proposals.
Ruling party leader Narendra Borkar, accompanied by around 60 BJP corporators, recently met Municipal Commissioner Vipin Itankar and raised serious concerns over the pendency of development proposals under the new work module system. The delegation reportedly sought intervention to accelerate the processing of files and remove the bottlenecks holding up local development projects.
Leader of Opposition Sanjay Mahakalkar has also announced that he will raise the issue at the forthcoming general body meeting. The Opposition is expected to demand an explanation from the administration over the extraordinary delay in processing approved works and its direct impact on development activities across the city.
The political criticism reflects growing dissatisfaction over a system that was introduced to improve efficiency but has, at least during its initial implementation, slowed down the movement of proposals.
Code of conduct and new module blamed for delays
Officials have attributed the massive backlog partly to administrative disruptions during the current financial year. Two separate periods of the Model Code of Conduct imposed in connection with Legislative Council elections reportedly consumed nearly three months, restricting the pace of civic decision-making and development-related activities.
The introduction of the new work module added to the difficulties. Employees accustomed to the earlier procedures are still familiarising themselves with the new system, resulting in delays at different stages of file processing.
However, these explanations have done little to ease the frustration of corporators, particularly when hundreds of projects have already received administrative clearance but remain trapped before the tendering stage.
“The nearly 900 files have received administrative approval but are yet to reach the tendering stage. If work orders are not issued within the remaining period, these projects will have to be carried forward to the next financial year along with their liabilities,” an official familiar with the developments said.
Budget targets under pressure
The backlog has also raised concerns over the NMC’s financial management and its ability to translate ambitious budgetary allocations into actual development on the ground.
Against the budgetary target of approximately Rs 6,200 crore set by Standing Committee Chairperson Shivani Dani-Wakhare, the administration must now reassess departmental expenditure, pending commitments and the allocations required for the coming financial year.
The Finance Department’s latest circular is intended to obtain a realistic assessment of expenditure under the current budget and determine the requirements for 2027-28. However, the exercise also exposes the challenge confronting the civic body: preparing fresh budgetary projections while a massive volume of previously approved development work remains stuck in the administrative pipeline.
The immediate priority is to clear the pending files, complete tendering formalities and issue work orders before the March 31 deadline. Otherwise, the NMC risks entering the next financial year with a substantial backlog of unfinished procedural work, mounting financial commitments and development projects that exist on paper but have yet to take off on the ground.
For a civic body projecting a budget of around Rs 6,200 crore, the inability to move nearly 900 approved projects even to the tendering stage is an embarrassing indictment of its administrative efficiency. The real test of the NMC’s development agenda will not be the size of its budget or the number of projects it sanctions, but how many actually reach execution.