Published On : Thu, Nov 21st, 2013

Itwari Dahibazar flyover to remain shut for 3 days

Advertisement

2013-07-30Nagpur News: The Itwari Dahibazar flyover would be shut for the next three days for the ongoing construction work of the new flyover.
The work of lifting the massive girders and then placing them would be done on November 22. Apart from this several other important works that had been pending since the past several months would also be completed during the shut down.

According to officials, the work of lifting the girders may prove to be hazardous for passers by and it is due to this reason that decision of stopping traffic has been taken.

Deputy commissioner (Traffic) Chandrashekhar Mina issued a notification in this regard and informed the NMC administration.

The traffic coming from Chandrashekhar Azad chowk towards Dahi Bazar would be diverted from Telephone exchange sqaure.