Nagpur: MahaRERA Issues Notices to 391 Projects

Advertisement

Nagpur:  The Maharashtra Real Estate Regulatory Authority has issued show-cause notices to 391 housing projects in Nagpur for failing to submit mandatory quarterly progress reports (QPRs), putting a large section of the city’s real estate sector under scrutiny.

The action is part of a wider statewide drive, with authorities warning of strict penalties if developers do not comply within the stipulated timeline.

Nagpur Tops Vidarbha in Notices

The move is part of a larger crackdown involving 8,212 projects across Maharashtra. In the Vidarbha region alone, 483 projects have been served notices, with Nagpur accounting for the highest share at 391.

Other districts include:

  • Amravati: 135 projects
  • Chandrapur: 113 projects
  • Bhandara: 104 projects
  • Akola: 12 projects
  • Buldhana: 10 projects
  • Wardha: 10 projects
  • Yavatmal: 4 projects
  • Washim: 4 projects

Why Action Was Taken

MahaRERA stated that developers failed to file Quarterly Progress Reports for the January–March period, a requirement under the Real Estate (Regulation and Development) Act.

Advertisement

These reports are essential for:

  • Tracking project progress
  • Monitoring financial transparency
  • Informing homebuyers about construction and fund usage

60-Day Deadline for Compliance

Developers have been given 60 days to respond to the notices. Failure to comply may lead to:

  • Cancellation of project registration
  • ₹50,000 penalty for reactivation
  • Ban on marketing, advertising, and sale of units
  • Freeze on project-related bank accounts

Focus on Buyer Transparency

According to MahaRERA norms:

  • 70% of funds collected from buyers must be kept in a separate escrow account
  • Withdrawals require certification from an engineer, architect, and chartered accountant
  • Even in case of no transactions, a ‘NIL’ report must be filed

Authorities said non-compliance with these requirements is considered a violation of homebuyer rights.

Impact on Nagpur Real Estate Sector

The action is expected to have a direct impact on developers in Nagpur, increasing compliance pressure and potentially affecting ongoing project marketing and sales.

Experts say the move could improve long-term transparency but may lead to short-term disruptions in the market.

What Happens Next

  • Developers must submit pending QPRs within 60 days
  • MahaRERA will review responses and decide further action
  • Buyers are advised to track project updates through official channels

Advertisement
GET YOUR OWN WEBSITE
FOR ₹9,999
Domain & Hosting FREE for 1 Year
No Hidden Charges
Follow Nagpur Today on Google
Add Nagpur Today to your Preferred Sources on Google to see our latest news more prominently in Search.